Guaranteed maximum price for construction contracts
A guaranteed maximum price (GMP) is a form of agreement with a contractor in which it is agreed that the contract sum will not exceed a specified maximum.
Typically, this is a mechanism used on design and build contracts where the contractor has responsibility for completing the client’s design and for carrying out the construction works, so they are in a good position to control costs.
If the actual cost of the works is higher than the guaranteed maximum price, then the contractor must bear the additional cost. If the cost is lower than the guaranteed maximum price, then the contract should set out whether the savings made go to the client, to the contractor or are shared. This can create a ‘pain/gain’, or a target cost agreement, where the contractor is incentivised to make savings, but the client has the security of a cost cap.
Effectively, this sort of contract transfers risks for delivering the project from the client to the contractor. For example, if events such as exceptionally adverse weather or strikes occur, or if items that might otherwise have been the subject of provisional sums (such as complex groundworks, the nature of which cannot be determined until the ground is opened up), which on other forms of contract might have resulted in a claim by the contractor for loss and expense, on a guaranteed maximum price contract, the contractor has to bear any additional costs.
As a consequence the contractor is likely to tender a higher price. Effectively they price the risks that they are taking on. This may be acceptable to the client if their priority is certainty rather than the lowest possible cost, for example, if the client has fixed funding available that cannot be exceeded.
However, a guaranteed maximum price is not a panacea, and the price is not necessarily fixed. If the client requests ‘extras’, for example, if the scope of the works increases, then the contract must provide for the price to be increased. Similarly, if work is omitted, then the price should be reduced.
There is obviously scope here for disagreement about what constitutes a change that should result in a price adjustment, and there is the potential for the contractor to use the valuation of changes to recover costs they have incurred elsewhere. This can cause tension in a form of contract that was selected to provide certainty.
In deciding whether to seek a guaranteed maximum price, the client should assess the nature of the project, the likely risks and whether it is sensible to expect the contractor to bear those risks. If risks are priced by the contractor, but then do not transpire, the client will have paid for nothing, whilst if serious unforeseen problems are encountered, the contractor may attempt to find a way out of their obligation, or may be at risk of insolvency.
Whilst a simple project on a greenfield site might be suitable for a guaranteed maximum price, works to existing, older properties, or complex projects with inherent uncertainty (in particular in relation to ground works) might not. To assess these risks, it is important to ensure that proper investigations are undertaken and a fair apportionment of risks made. It is also important to ensure the client’s requirements have been clearly defined to avoid potential dispute about the nature of the works. A guaranteed maximum price is not an excuse to leap into the unknown and hope for the best.
Guaranteed maximum price contracts tend to be either bespoke (on small projects, often written by the contractor, and so potentially including hidden get-out clauses), or modified standard form contracts – which themselves have potential risks. It is important that these contracts have unambiguous wording, particularly where there are pain/gain provisions.
Despite the name ‘guaranteed maximum price’ the client should still ensure that they have an adequate contingency.
[edit] Related articles on Designing Buildings
- Construction contracts.
- Construction manager at-risk.
- Contingency.
- Contract sum.
- Design and build.
- Fixed price contract.
- Guaranteed maximum price with target cost.
- Force account work.
- Loss and expense.
- Lump sum contract - pros and cons.
- Modifying clauses in standard forms of contract.
- Price.
- Procurement route.
- Provisional sum.
- Relevant event.
- Target cost contract.
- Time and material contract (T&M).
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.